Construction work
phase by phase

Follow the progress of Gösta's extension project  in our photographic diary. You will find the updates on the right, latest update on top edge.

  • Liimpuurunko2.jpg
  • Liimapuupalkit1-pieni.jpg
  • Rakennuksen-runko.JPG
  • Rakennuksen-runko-sisa-ta-.JPG
  • Sisa-tila-rajattu.jpg
  • Laajennus-etupuolelta.JPG
  • Laajennus-takapuolelta.JPG

Thursday 24. October 2013

Walls in visual rhyme

At the end of October the appearance of Gösta’s pavilion is starting to take more visible shape as over half of the glulam beams i.e. “mullions” have been put to place. After their installation the remaining roof work can be completed. The heating is on throughout the building and finishing casting of the floor areas are in good progress, also electrical and ventilation installation is in good speed. The recent landmark, tower crane, will disappear from the work site by the end of November. Landscaping work has been begun with the parking areas and paths at the shore-side. At present, about 65 persons work for several contractors on the site. Image: Juha Roponen


Friday 27. September 2013

Window installation on progress

At the end of September Gösta's contruction progresses with installation of quite a few windows. In the basement the heating is already on, and in other parts of the building by mid-October. The floor surface casting is going on in office, restaurant and exhibition spaces. Elsewhere the partitions are being masoned. On the outside, the roofing is already nearly completed. The foundation of the supporting wall has been casted. The installation of mullions will be started around the end of September. In the first phase of the landscaping the aim is to renovate the areas further away from the building. In all 55 persons are working at the site. Image: Juha Roponen


Tuesday 27. August 2013

A tent protects the roof makers

At the end of August the work at Gösta extension is done everywhere from the basement to the roof. The new museum building has been covered with a tent under which the roof is constructed. The framework of the large window surfaces are installed at the same time. The supporting structure of the corridor connecting the reception area to the rest of the museum has been put in its position. In the basement the finishing and painting of the inner walls is in progress. The ventilation units are installed in the technical space. Image: Juha Roponen


Tuesday 30. July 2013

The spaces begin to take shape

At the end of July it is already easy to grasp the shape of the new Gösta. In this picture you can see the main exhibition space that is at the beach side of the building. Work at the extension prceeds in a slightly different pace in different parts of the building. At the beach side, the installation of walls and windows is at good speed. As next  the floor between the office space and exhibition space will be casted in the midsection of the building. The floor of the part of the building that is at the top of the slope has been casted and the last glulam frames are being erected. Image: Juha Roponen


Friday 5. July 2013

Wall elements to place

In July the new Gösta has already a clear shape. The construction of the three different parts of the extension proceed in different pace. The part that is most advanced has already a frame made of glulam beams. The erection of wall elemets is in progress. Image: Juha Roponen